Thursday, December 10, 2020

Power connection fees spike as govt withdraws subsidies


tech01pix

Customers in need of connection will now meet the full cost of accessing electricity. PHOTO | FILE

By Christine Kasemiire

Electricity connection costs approved by Electricity Regulatory Authority (ERA) have spiked as government withdraws subsidies that were keeping the costs at bay. 

The costs, which range between Shs570,000 and Shs3.4m, have been approved by ERA after a policy directive issued by Ministry of Energy allowed financially capable customers to pay electricity connection costs following months of restriction, under bondage to government’s free Electricity Connection Policy (ECP).

However, the new costs are much higher than the costs charged by Umeme, the country’s major power distributor before introduction of the ECP in 2018.

Prior to ECP, customers who didn’t need a pole to get connected paid  Shs98,000 for connection and Shs41,300 for inspection. 

The new costs, on the other hand, indicate that a no pole and single phase connection will require Shs576,773 for a wired pre-paid split metre and Shs610,918 for a wireless pre-paid split metre. 

Mr Julius Wandera, the ERA director of corporate and consumer affairs, yesterday said as the regulator they set uniform connection fees for distributors such as Umeme. 

Advertisement

However, he noted previous connections under Umeme had been subsidised by government even before ECP. 

“Government has always subsidised connections, especially for grid connected customers. The introduction of the ECP was now beyond subsidisation but a free connection. The newly approved connection charges are a true reflection of the cost of making a connection on the market;” he said. 

New costs 

Customers who do not require a pole, but need a three phase connection (much higher voltage), for example millers and small scale industries, will part with an amount between Shs2m and Shs3.4m.

While customers that require one pole and a single phase connection, for example supermarkets and residential places, will pay between Shs1.9m and Shs2.3m. 

The difference between single phase and three phase is that the former requires two wires, while the latter works through three wires. 

Single phase is also lower voltage electricity, mainly used in households compared to three phase, which is used by industries. 

The connection costs, ERA said, are inclusive of Shs8,000 payable to Uganda National Bureau of Standards for metre testing.

Even then, customers will need to pay transport costs and inspection fees, which signifies that a customer in need of a no pole single phase connection with a wired pre-paid split meter will pay Shs668,073 for connection.

The new costs come after amending the ECP, which for months restricted customers from fully paying for own connections despite government failure to fund them. 

“All electricity distribution licensees [or] service providers are directed to allow new consumers to pay for their connections based on the following: Applications for electricity connection on single phase no-pole and one-pole service shall clearly indicate whether they are willing, able and ready to pay for their connection cost or whether they wish to wait for government funding,” the notice signed by Ms Ziria Tibalwa Waako, ERA chief executive officer, reads in part.

Government in November 2018 launched the ECP with the view of subsidising last mile electricity connection to connect 300,000 customers annually. 

Under ECP, customers only pay Shs20,000 for inspection while government caters for the rest of the connection fees. 

However, the 10-year project spearheaded by Rural Electrification Agency run out of funding less than two years of its implementation partly due to a shift in financing  priorities to Covid-19.

Worth noting, the ECP was created because of complaints by customers of high power connection fees charged by power distributors, which range between Shs98,000 and Shs2m.

 

No comments :

Post a Comment