Summary
- The news that the government has paid more than Sh7 billion in penalties to investors behind the Lake Turkana Wind Power project is the latest example of badly negotiated deals that end up exposing the taxpayer to huge losses.
- The payment may be legal. But in terms of opportunity cost, payment of a contractor claim running into billions for no value or service is a national scandal.
- According to the arrangement with the investor, Lake Turkana Wind Power was to build the power plant.
- The government, through the State-owned Kenya Electricity Transmission Company (Ketraco), was to build the transmission line.
The news that the government has paid more than Sh7 billion in
penalties to investors behind the Lake Turkana Wind Power project is the
latest example of badly negotiated deals that end up exposing the
taxpayer to huge losses.
The payment may be legal. But
in terms of opportunity cost, payment of a contractor claim running into
billions for no value or service is a national scandal.
‘How
Kenya paid Sh7 billion for non-existent power’ was the headline of a
story reported by the Daily Nation yesterday. We lose billions in
taxpayer money every year in payment of claims and pending bills arising
from poorly negotiated contracts and lopsided agreements with
investors.
Here is a brief background to this saga.
According
to the arrangement with the investor, Lake Turkana Wind Power was to
build the power plant. The government, through the State-owned Kenya
Electricity Transmission Company (Ketraco), was to build the
transmission line.
It was a 430-mile high-voltage transmission line running from
Loiyangalaini in Marsabit County to a substation in Suswa in Narok
County, which is the country’s main interchange for electricity coming
from the West of the country.
As the parties were
negotiating, the investors calculated that there was a high probability
that the building of the power line would be completed faster than the
transmission line.
Which is why during the talks, they
forced an arrangement to cover themselves against delays in completion
of the transmission line.
To cover themselves further,
they bought an insurance from the African Development Bank (AFDB) to
cover them against failure by the government to pay the penalty for
delay in completion of the transmission line.
The stage had been set for payment of the billions.
I
blame the parties who were negotiating on the government’s behalf
because the arrangement they entered into amounted to gifting the
investors a blank cheque.
Why do I say so? Because
anybody who looked at Ketraco’s records of completing projects seriously
would not have put their signature on such a pact.
Did
these guys look at the problems and difficulties the State-owned
company was experiencing with land acquisition and with securing way
leave?
This was a transmission line that was going to traverse many counties.
Indeed, land acquisition was going to be problematic because the right of way was going to be 428km long and 60m (metres) wide.
Worse, the construction of the line was to result in involuntary displacement of thousands of people.
I
ask again: Why couldn’t those negotiating for the government ask the
investors to buy an insurance or seek other forms of risk guarantees?
Why were we going out of our way to give this project so much
accommodation since the policy of the government at that time was not to
give sovereign guarantees to investors?
If the parties
negotiating on behalf of the government had taken their time to study
the problems and the trends in acquisition of land and way-leave for
large infrastructure projects in this country, they would not have
signed on the dotted line.
PAYMENT COMPLAINTS
Worse
still, events that followed during the construction of the transmission
line – perhaps coincidentally — only worked to favour the investor’s
interest and to ensure that it scooped billions in penalties.
In
the middle of the construction of the transmission line,
sub-contractors started complaining that Ketraco’s contractor — Isolux
of Spain— was not paying their invoices.
Months later,
and even as signs showed that Lake Turkana Wind Power was hurrying to
complement construction of the power plant, Isolux was declared bankrupt
in its own country, Spain.
The penalties under the
agreement with the governor had crystallised. We need to strengthen our
capacity in negotiations with investors.
No comments :
Post a Comment