Dodoma — TANZANIA's
access to electricity index has recorded the highest level so far with
84.6 per cent in 2020, as authorities have vowed to intensify the rural
electrification model, to boost the
speed and efficiency of getting
power especially to those lacking the facility.
The number of villages with access to electricity rose to 9,112 in April 2020 from 2,018 in 2015.
Energy Minister Dr
Medard Kalemani told the National Assembly in Dodoma, the country's
overall electricity access had reached 84.6, up from 67.8 per cent in
2016.
The number of
customers connected to the main source of power also reached over 2.766
million, up from 1.473 million, or an increase of 1.293 new connections.
Tabling his
ministry's 2.196trl/- budget focusing on increasing investment in power
production and supply, the minister says power generation in the country
had also increased to 1,601.84 megawatts as of last April from only
1,308megawatts in 2015.
The increase in
power capacity is attributed to the completion of Kinyerezi I and II
natural gas-powered station generating a combined capacity of
398.22megawatts.
Natural gas in the country's largest source of power mix accounting to 892.72 megawatts of the national grid.
Hydropower
contributes 573.70 megawatts, while heavy oil and biomass make up of
88.80 megawatts and 10.50 megawatts, respectively.
Dr Kalemani told
the parliament that works on the construction of the mega Julius Nyerere
Hydropower Project (JNHPP) that will pump in addition 2,115 megawatts
into the national grid has reached 85 per cent and will be completed in
2022.
"We are planning to
continue implementing other electricity- generating projects during the
forthcoming financial year," he said.
The lined-up
projects include the ongoing Rusumo Hydropower Project - a shared
project between Tanzania, Rwanda and Burundi whose work has now reached
61 per cent.
It will generate 80
megawatts upon its completion in February next year that will be shared
among the three countries, and Tanzania has allocated 13.846m/- for the
final works.
"At least 1.44trn/- has been allocated for the JNHPP during the financial year 2020/21," the minister said.
Dr Kalemani
outlined that the government has so far paid 1.219trn/- as part of the
6.55trn/- needed by the contractor to complete the job.
However, he noted that the project has been going on well, having employed some 3,897 people.
He named other
projects that will be implemented in 2020/21 as Ruhudji project (358
megawatts), Kakono (87megawatts), Rumakali (222 megawatts), Malagarasi
(45 megawatts), Kikonge (300 megawatts), Kinyerezi I Extension
(185megawatts), Mtwara (300megawatts) and renewable energy projects
(Solar 150megawatts, Wind 200 megawatts and Coal 600 megawatts).
"We're committed to increasing our power distribution networks," he added.
He cited some
projects as the 400kV Singida-Arusha- Namanga, 220kV Makambako- Songea,
220kV Bulyanhulu- Geita, 220kV Geita-Nyakanazi, 220kV Rusumo-Nyakanazi,
and 400kV Iringa-Mbeya-Tunduma- Sumbawanga-Mpanda- Kigoma-Nyakanazi,
which is commonly known as Northwest grid.
He said the
government's backed rural electrification phase three round one that
targeted to connect 3,559 villages at a cost of 1.157trn/- had so far
connected 2,659 villages.
"We have embarked
on electricity densification project targeting urban suburbs that had no
power. The project targets Dodoma, Kilimanjaro, Pwani, Tabora,
Shinyanga, Mwanza, Singida, Tanga and Mbeya regions," he said, saying a
total of 1,103 suburbs will benefit.
According to the
minister, the State is also implementing peri-urban projects and
renewable energy projects targeting off-grids and at least 29bn/- and
333.43bn/- have been allocated in the 2020/21 budget for the purpose.
No comments :
Post a Comment