Tanzania’s standard gauge railway (SGR) will undergo its first
formal testing in May, after the completion of the construction of the
first phase in April.
Speaking to The EastAfrican in
Dar es Salaam this week, SGR project manager Machibya Masanja said
construction is going on around the clock to meet the April deadline.
He
said test runs will be held over three months before the railway’s
official inauguration, which will allow goods and passenger services to
commence.
The first phase covers 300 kilometres from Dar es Salaam to Morogoro, and is 72 per cent complete.
It
was initially scheduled to be ready last November, but heavy rains
disrupted the works. The meteorological department has issued a warning
of heavy rainfall expected in March and April.
The
first deadline was missed when the drilling works for a tunnel near
Morogoro, building of bridges and placement of culverts were paralysed
by heavy rains.
The first phase will have six main stations at Dar es Salaam,
Pugu, Soga, Ruvu, Ngerengere and Morogoro, with the Dar es Salaam and
Morogoro stations being the largest.
Mr Masanja said
construction works on the second phase of the project, covering 422
kilometres from Morogoro to Makutupora in Dodoma, started four months
ago and 20 per cent of the work is done.
Contractors
Yapi Merkezi of Turkey and Mota-Engil Africa of Portugal are jointly
handling the first and second phases of the project, but separate
tenders will be floated for the three remaining phases of
Makutupora-Tabora (294km), Tabora-Isaka (133km) and Isaka-Mwanza
(248km).
The 1,457km-long SGR project is estimated to cost $7.5 billion, with $600 million spent so far.
In
December, Tanzania Railway Corporation director general Masanja
Kadogosa said the railway will be extended to Rwanda and Burundi.
No comments :
Post a Comment