IN the past four
years, the government has managed to add 480MW in the national grid, a
move that has enabled the country have a surplus of 280MW.
The additional
megawatts are the results of the completion of various power projects
including the
gas-fired Kinyerezi I and Kinyerezi II plants, the
Minister of Energy Dr Medard Kalemani revealed yesterday.
The power in the national grid has also increased to 1602.34MW this year, up from 1038MW that was recorded in 2015, he added.
The minister issued
the statement yesterday as he was explaining on the feats recorded by
the docket over the past four years under President John Magufuli's
regime.
He said the
government has also been rehabilitating electricity infrastructures
including transmission lines, hence reduce the frequency of power-cut
compared to the past.
"We have
constructed a high voltage transmission line of 400KV on a 670km line;
Iringa to Shinyanga via Dodoma and Singida, and 200KV line from
Makambako - Madaba - Songea in Ruvuma region," he said.
The next project
will be the construction of the1384km long of 400KV transmission line
from Mbeya-Tunduma- Sumbawanga-Mpanda through Kigoma to Nyakanazi,
revealed Dr Kalemani.
Again, each region
in the country has been distributed with 2.5bn/- for rehabilitation of
electricity infrastructures, he said. On the other hand, the ministry
has managed to connect 12 centres that were using diesel powered engines
to the national grid, as a result power company, Tanzania Electric
Supply Company Limited (Tanesco) has saved a total of 138bn/- out of it.
After cancelling
the power generation contract with Symbion, Aggreko and Independent
Power Tanzania Limited (IPTL) Tanesco has managed to save 6.9bn/- that
it was incurring monthly from the deal.
"Now, Tanesco is
neither a loss making company nor dependent from the central government.
The entity operates by using its own funds and for the first time it
has managed to issue a dividend of 1bn/-," he explained.
To minimize cost of
connecting electricity, the government took efforts to ensure that all
the essential equipment needed to install the service are manufactured
in the country, stated the minister.
"The list of
equipment that are now manufactured here includes Luku metres,
electricity poles, cable wires, transformers. More investors are
welcomed to run open accessory- making factories," noted Dr Kalemani
adding that the factories among other things create job employments for
local people.
So far, about 3400
Tanzanians have been employed in the factories that produce electricity
poles and by stopping to import electricity poles from South Africa, the
minister said, Tanesco has also managed to save a total of 162.23bn/-.
About power supply
in rural areas, the minister said a total of 8,587 villages have been
connected to power project from Rural Energy Authority (REA), out of
12,000 villages in the country.
By June 2021 all
villages in the country will be supplied with electricity as it was
promised by President Magufuli, and that tariffs of electricity will
continue to go down, reaffirmed Dr Kalemani.
He went on to
explain that, it has never happened before in history to have a district
that has full coverage of electricity in all villages.
"But this time the
government has made it, there are 34 districts that are fully covered
with power supply, same spirit will go countrywide," he said, adding
that a total of 11,070 public institutions have also connected to
electricity between 2015 and 2019, up from 3,200 that were enjoying the
service in the past.
No comments :
Post a Comment