Dar es Salaam — The
government is reviewing the contracts for Mchuchuma and Liganga
projects to align them with the...
amended natural wealth and resources
laws.
The ministry of
Trade, Industry and Investment's deputy permanent secretary, Rudovoik
Ndurie, told The Citizen in an interview that all strategic projects in
the extractives sector - including those in the mining, gas and oil
sectors - are undergoing reviews.
"This is after the
government enacted the new laws in the extractives sector and
implementation of the directives given by Parliament to align all
natural resources contracts with the new laws," he said.
Answering a
question on whether the government is in new negotiations with the
Tanzania China International Mineral Resource Ltd (TCIMRL), he said he
was not aware if that were happening.
However, he said he
was aware that last year the government planned to appoint a
negotiation team to revisit terms that were different from the initial
contracts.
Earlier, the TCIMRL
chief executive officer, Eric Mwingira, told The Citizen that they were
in new negotiations with the government.
Also Read
Queen, Prince Harry, senior royals set for crisis meeting
Gloves are off in Uhuru, Ruto political contest
Anxiety reigns as Simba eye Mtibwa scalp
This was after the $3 billion (Sh6.8 trillion) Mchuchuma and Liganga projects had taken at least nine years to take off.
"The company has invested a lot in the project, and what we can do is wait for the government to make a decision," he said.
He explained that they were currently in talks with some government officials who had been appointed to oversee the matter.
However, he
declined to mention what was being discussed on the grounds that it was
still too early to make the discussion public.
The Liganga iron
ore and the Mchuchuma coal mining and power projects, worth $3 billion,
were expected to be implemented by TCIMRL beginning in 2016.
TCIMRL expected to
invest $1.8 billion in Liganga to establish an iron ore mine and iron
and steel complex to produce one million tonnes per year of iron and
steel products, as well as vanadium pentoxide and titanium dioxide.
The Mchuchuma
project includes the construction of a 600MW coal-fired power station,
of which 250MW would be used by the iron plant, while the remaining
350MW would be fed to the national grid.
Reports state that,
in February last year, Minerals minister Doto Biteko issued a 30-day
ultimatum to the National Development Corporation (NDC) to "rectify
mistakes" in the mining contract - or the licence would be revoked.
But TCIMRL had told
The Citizen that the project - whose contract was signed in 2011 -
would be up and running by now had the government not dilly-dallied in
endorsing tax incentives requests.
He said Mchuchuma
would be producing electricity after three-and-half-years of
construction, while Liganga would be nearing completion this year after
four years of implementation.
In November 2018,
the Chinese company revealed that it was being held back by the Treasury
delaying approval of incentives negotiated with the government in 2015.
The company won the
tender for the mega-project that has the potential to create 5,000
direct jobs and 30,000 indirect ones in 2010. But its roll-out has been
beset by red tape to-date.
According to Mr
Mwingira, the company was only asking for a 10-year tax relief for a
project whose lifespan stretches to between 50 and 100 years.
He said that, among
other things, the company was seeking tax incentives on import duty on
goods to be imported for the construction work, as well as incentives on
spare parts and machinery. It was also asking for tax relief on fuel.
The Chinese firm's
parent company, Sichuan Hongda Group Ltd (SHG), discharged its part of
the contract by carrying out geological exploration, environmental and
social impact assessment, valuation for purposes of compensation of
people affected by the project, research, as well as development for
smelting technology to the tune of about $70 million.
"The capitalised
exploration cost consumed a lot of resources because of the complexity
of the mineralogical constitution - when it comes to separation of
titanium from iron ore - and design for industrial complex for power
generation for iron and steel industry," said Mr Mwingira.
Immediately after
the granting of the licence, TCIMRL started negotiations with the
government of Tanzania in 2014 through the National Investment Steering
Committee (NISC) on the granting of investment incentives for the
Mchuchuma and Liganga projects, in accordance with the provisions of the
Tanzania Investment Act (CAP. 38).
"After concerted
negotiations, a Performance Contract was signed in June 2014, which
provided for some investment incentives for the project."