By Peter Saramba
Mwanza — President
John Magufuli has revealed the secret behind the stalling of some
strategic projects including the construction of Mwanza Main Market and
the new bus terminus in Nzega and Nyegezi respectively.
Speaking to
residents of Nzega today November 27, while on his way to Shinyanga,
President Magufuli has said funds allocated for the implementation of
those projects and others in some districts and regions in the country
have been diverted to other projects which are more profitable.
"Not only the Nzega
Bus Terminus, but also Nyegezi in Mwanza. The Mwanza Regional
Authorities planned to construct a new and top-class storeyed main
market....I don't know whether someone can sell tomatoes on a top floor!
We have diverted the funds to other projects which are more
profitable," said President Magufuli.
The City of Mwanza
had planned to implement the construction project of a new
state-of-the-art two storeyed main market building with 500 rooms and
1,500 stalls for entrepreneurs and a parking lot for 500 vehicles. The
project was set to cost over Sh23 billion.
According to the
Director of the Mwanza City Council, Kiomoni Kibamba, the new Nyegezi
Bus terminal project would have cost Sh14 billion.
The Mwanza City
Council had also planned to spend over Sh13 billion to implement a
construction project on a parking lot for trucks in Buhongwa.
Also Read
Kabudi steals the show at Bomas of Kenya as he urges fight against tribalism
Tanzania to support Kenya in its UN Security Council candidature
Namibia votes in test of ruling party's grip on power
According to
Kibamba, all the three projects would have been part of some strategic
projects in the country, which have been put on hold by the government
until further notice.
No comments :