Tullow Oil will from next month increase the number of trucks
ferrying oil from Turkana to Mombasa from the current 30 to 100 after
the firm went into mini crude production.
The British
oil explorer said the start of its Early Oil Pilot Scheme crude
production on May 6th is expected to hit the 2,000 barrels per day
target in June, tripling its trucking needs.
Tullow Kenya Managing Director Martin Mbogo told the Nation
that although trucking of crude, which started in June 2018 was
envisioned to go on for about two years, it may be extended depending on
project needs.’
“The current plan is to conduct EOPS
trucking for approximately 18-24 months. The schedule could, however,
change in the future in line with the project needs. During EOPS phase
one, about 30 trucks were in use. This figure is expected to gradually
rise to a maximum of 100 trucks at the peak production of 2000 barrels
per day,” Mr Mbogo said.
The involvement of more trucks
will mean more expenditures in the multi-billion shilling experiment
meant to try Kenya’s crude in refineries overseas.
It
will, however, be good news to the suppliers of trucks and the special
tank-tainers used to ferry the waxy crude which needs to remain in
heated form all through the more than 800 kilometres journey.
Kenya hopes to fill the first shipment of its crude to be tested
in the international market in the third quarter of 2019 but details of
who is expected to buy the crude remain hazy.
Experiment
The
Kenya Civil Society Platform on Oil and Gas, which described the scheme
to truck crude oil to Mombasa to test the country's crude as a ‘Sh4
billion loss experiment’ in 2016 said the plan to export crude oil may
still meet various hurdles.
KCSPOG Coordinator Charles
Wanguhu said construction of the 821-kilometre crude oil pipeline may
take longer given the outstanding issues in the ongoing negotiations
between the parties Involved, which may delay the crucial Final
Investment Decision.
"Tullow
has put the target for the final investment decision later this year
while the Front End Engineering Design (FEED) for the pipeline took
quite some time. It means things will only start unfolding faster after
the first shipment followed by the FID and then the financing of the
crude pipeline," Mr Wanguhu said.
The Tullow manager, however, said the pipeline FEED was on target after it completed in February 2019.
“Currently, we are carrying out extra work post FEED to give a higher confidence factor on cost and schedule,” Mr Mbogo said.
No comments :
Post a Comment