National Assembly Public Investments Committee members on a tour of the
Hazina Trade Centre building project yesterday. photo | jeff angote
A Chinese contractor has slapped the National Social Security
Fund (NSSF) with a Sh6.9 billion
compensation claim for the stalled construction of a 39-storey building in Nairobi’s city centre.
compensation claim for the stalled construction of a 39-storey building in Nairobi’s city centre.
Work stopped on the 15th floor and China Jiangxi has so far been paid Sh2.5 billion for the project.
The
NSSF hired the Chinese firm to finish building the 39-storey tower,
which already had eight floors, including the four that housed Nakumatt,
between June 2013 and July 2016.
The troubled
supermarket chain moved to court four years ago and blocked the building
of additional floors above its Nakumatt Lifestyle Branch on grounds
that the construction was disrupting its business.
NSSF
has rejected the Sh6.9 billion claim and a consultant has recommended
that the Chinese contractors be paid Sh20 million per week as
compensation for the additional 94 weeks they have been on the site,
translating to Sh1.8 billion.
The breakdown of the
compensation includes Sh8.7 million for expenses, Sh9.8 million for idle
plant and equipment at the site and Sh1.7 million for other losses.
The Public Works Ministry will in two weeks provide the rightful share owed to China Jiangxi.
“The
current claim under evaluation at this moment is Sh1,890,648,193.62
which would accumulate at the rate of Sh20 million per week should the
project stall again,” Anthony Omerikwa, the NSSF managing trustee told
MPs on a visit to the site.
The compensation is based on an assessment by Tana & Associates, a quantity surveyors consultancy.
The
NSSF has decided to cap the building at the 15 flours, lowering the
construction to about Sh4 billion from the initial cost of Sh6.7
billion.
The troubled supermarket chain moved to court
four years ago and blocked the building of additional floors above its
Nakumatt Lifestyle branch.
The retail chain blocked NSSF contractors from reinforcing columns inside the store for additional floors.
Auditor-General
Edward Ouko last year recommended legal action taken against Nakumatt
to end the blockade. But the cash-strapped retailer was evicted from the
building in December for failure to pay rent, paving the way for
resumption of construction.
Yesterday, Mr Omerikwa told MPs that terminating the contracts will expose NSSF to costly litigation and penalties.
No comments :
Post a Comment