When the
Electric Power and Lighting Company and the Nairobi Power and Lighting
merged in 1922 to give birth to the electricity sub sector, Kenya’s
priority was far from deepening connection to any significant portion of
its population.
The country had a narrow manufacturing sector and the population was below 2.5 million whose main sources of power was biomass.
Today,
the population has grown more than 17 times and with the expansion of
the economy came the change in lifestyles, raising demand for
electricity and presenting the country with a huge headache to meet the
ballooning needs at an affordable rate.
The government
is already in a tight race to meet two ambitious plans by June 2017;
connect 70 per cent of households to the main grid and add 5,000MW of
installed capacity to the system.
The big challenge now
lies in managing the future generational mix as well as consumption
patterns of the new entrants to the grid, which has been rapid in the
last three years, deepening the complexity.
Already 55
per cent of households have been hooked to the main grid, representing
about 25 million people as the government banks on the Last Mile
connectivity programme to achieve the universal power access plan by
2020.
With 22,245 schools connected to power and
another 1,000 in the next few months, 35 towns and urban centres in 27
counties have been lit since 2013 under the Sh7.6 billion
street-lighting programme targeting 65 major urban centres across the
country, the challenge ahead is real.
Smart Company
delved into the future of the country’s largely renewable generation
mix, which has been lauded internationally to find out whether Kenya’s
plan will need a shift of focus on the generation mix.
Will
the country continue to enjoy both cheaper and greener power amidst the
growing connectivity? How about stability of the power and what
diversification is required in the mix to meet the ambitious plans?
The
Energy Regulatory Commission director-general Joseph Ng’ang’a said the
country has been enjoying the largely renewable sources combination due
to the low installed capacity and the low demand over time.
According
to Mr Ng’ang’a Kenya will have to be strategic in determining which
sources will fit the projected demands at the least cost to keep power
accessible and affordable.
“Based on our focused
consumption, including the new industries coming into the power demand
structure like the Konza City, electrification of the SGR, the special
economic zones, and growing middle class with people having more
equipment, we have to look at how to meet these demands at the least
cost way possible,” Mr Ng’ang’a said.
“With this then
we may need to add say 1,000MW into the grid. Now the largest geothermal
plant we have produces 70MW, meaning we may need several of these to
generate the 1,000MW.
Coal, which starts from 300MW in
one plant would, for example, be ideal if you want to get the economies
of scale.” Kenya is also said to have enjoyed the installation and use
of geothermal sources because of their low operational costs and their
high load factor (meaning they can run almost non-stop).
The
county has also been pursuing generation of nuclear power by 2033 with a
recent signing of an agreement between Korea Electricity Power Corp
(KEPCO) and the Kenya Nuclear Electricity Board being a major boost in
the 4,000MW scheme.
Mr Nga’ng’a said the fears expressed over the plan are not realistic.
“You
see, the rule of the thumb in power generation is that the biggest unit
your system should not exceed 10 per cent of your installed capacity so
that in case it was to come out of the system then there would be no
crisis. That is why in our case we could only have allowed 150MW at
most. But that is changing and with the growing demand and the need to
keep costs low, these are the options we have,” he said.
Kenya’s
biggest plant currently is the 85MW Gitaru hydro plant. There are also
plans to put up a 981MW coal plant at the Coast as part of the scheme to
add 5,000MW into the national grid.
The country’
daily demand curve sees the majority of households using power during
the evening between 6-10 pm, which makes it hard to run the base
sources without involving the easy-to-start diesel powered plants at the
centre of the power purchase agreements.
South Africa,
which has 45,000MW of installed capacity has more than 90 per cent
sourced from coal. The country which projects to add over 40,000MW by
2025 is currently putting up another 9,600MW coal plant.
Kenya’s
coal plant expected to be constructed in Lamu County has been opposed
by community, citing environmental and health risks.
Data
from the International Energy Association indicates that most of the
developed counties have very low green energy mix, including the USA
whose renewable mix is below 10 per cent.
The ERC,
which is tasked with ensuring there is affordability, sustainability and
quality of energy to ensure that the country is competitive, however,
says there will be minimal risk as the sources will be properly vetted
by the authority before licensing.
No comments :
Post a Comment