PRESIDENT John Magufuli has directed the Tanzania Electric Supply Company Limited (TANESCO) to do away with ...hired electricity generating plants.
Instead, the Head of State has
instructed the state-run power utility to come up with constructive
ideas on how to set up their own power plants.
He made the directive in Dar es Salaam
yesterday during the inauguration of Kinyerezi II 240-megawatts combined
cycle power plant project, saying the country is rich in gas, uranium
and coal and wind energy for electricity generation - and hence no need
for unreliable supply.
"Hired plants are very expensive. They
are a big burden to consumers who have to pay more to compensate for the
high capacity charges, thereby benefitting the companies, which sign up
with Tanesco like it was the case with IPTL,” Dr Magufuli observed.
He added that there had to be a point
whereby the country could produce its own reliable electricity and be
able to sell the surplus to other countries - just like what some
countries are doing.
“That capacity is there,’’ the president
stated. Dr Magufuli directed the Minister for Energy and Minerals,
Professor Sospeter Muhongo, to work on the issue and always be wary of
experts who advise on the use of hired power plants to handle shortages.
"Experts or consultants who advise us to
hire power plants instead of buying our own are not fit for the job and
if possible, terminate them since they do not wish this nation well,"
President Magufuli further observed and directed.
Laying of the foundation stone for
Kinyerezi II 240-megawatt plant came a few months before the launch of
Kinyerezi I, which currently generates 150 megawatts with plans afoot to
extend its capacity to 185 megawatts. Dr Magufuli said the government
will inject 20 million US dollars for the extension of the project.
A total of 425 megawatts is going to be
achieved in the next two years when the projects will have been
completed. "I am told that discussions with investors on the
construction of Kinyerezi III 600 megawatts and Kinyerezi IV 330
megawatts are at an advanced stage.
You should work diligently to overcome
electricity challenges faced by the majority of Tanzanians by obtaining
reliable generation sources," noted the president.
He cautioned the Minister, Tannest
Managing Director and the Permanent Secretary (PS) in the ministry to
look for ways to preserve rain water so that hydro-power generating
plants won’t be affected during drought seasons.
Dr Magufuli said the remaining 2bn/-
compensation for the residents whose land was taken to pave way for the
implementation of Kinyerezi I would be issued.
He called upon two residents who refused
to receive their reimbursement to collect the money and if they are not
satisfied should go to court.
The government has set aside 30bn/- for
compensation. He extended appreciation to Japan, Word Bank (WB), the
African Development Bank (AfDB) and other development partners for their
continued support.
The president called on the contractors
to accomplish the project within the contract time and where possible,
before time; insisting, however, on quality, standard and value for
money.
"The contractors should also consider
hiring women and youth living in the area and cautioned them of any kind
of theft as it would be delaying the development of the country ," he
stressed.
Earlier, Prof Muhungo said the project
was going to be implemented through a soft loan of 344 million US
dollars, equivalent to 740bn/-, from the Government of Japan.
"Japan has injected 85 per cent of
project funds, which amounts to 292 million US dollars while Tanzania
has committed 15 per cent to the project, equivalent to 52 million US
dollars (110bn/-)," said Prof Muhongo.
The project will be implemented by
SUMITOMO Company from Japan and would be responsible for all the
engineering work and plant procurement.
"This project is going to be owned by
the government through TANESCO by 100 per cent, therefore the country
will be the sole-owner of the electricity being generated," he said.
Prof Muhongo said since the Fifth Phase
Government came into office, power generation has increased from 800
megawatts to 1,000 megawatts against the demand of 1,020 megawatts.
TANESCO Managing Director, Engineer
Felchesmi Mramba, noted that the project is going to use a new
technology identified as combined cycle, whereby electricity will be
generated from natural gas and the heat obtained from the plant, will be
used be used to boil water and generate electricity through vapour.
"The project will involve six plants
with the capacity of generating 160 megawatts generated from natural gas
and other two vapour plants generating up to 80 megawatts, bringing the
total to 240 megawatts," he noted.
On his part, the Japan Ambassador to
Tanzania, Mr Masaharu Yoshida, said for Tanzania to accelerate its
efforts in becoming an industrialised middle-income country as
envisaged, it was vital to possess reliable and quality electricity.
"I am sure Kinyerezi II will, upon
completion, usher in a new chapter in Tanzania. It will be the first of
its kind in all of East Africa," said Ambassador Yoshida.
No comments :
Post a Comment