Tanesco�s Managing Director Felchesmi Mramba
However, the power utility has dismissed Africa Intelligence’s
claim saying it was unfounded since running and switching on of the
plant’s gas-powered turbines was going on according to plan.
The turbines are expected to generate up to 150 megawatts as part
of Tanesco’s strategy to reduce dependency on hydro power and use of
expensive oils.
“According to our sources, Tanzania's Kinyerezi 1 power plant built
by Norway's Jacobsen Elektro and inaugurated in October is running far
under capacity,” Africa Intelligence reported last week.
Denying the allegation, Tanesco’s Managing Director Felchesmi
Mramba said that the plant was currently generating 72 MW with the
capacity set to increase this week after switching on another turbine.
According GE Power & Water's Distributed Power business, which
supplied the gas turbines for the project, the plant will increase
Tanzania’s installed power capacity by 20 per cent.
Under the terms of the contract, GE supplied four LM6000-PF
dual-fuel aeroderivative gas turbines, which will provide about 44.5 MW
of power each at about 40 per cent efficiency, the American company
said.
The project is a US$183 million investment running on gas from
Mtwara supplied through the Mtwara-Dar es Salaam pipeline. Its financing
was provided by the government through Tanesco, which is also
undertaking three other power projects in the area.
“The project is going on well and we now produce 72 MW, and next
(this) week we will switch on another turbine to increase the
efficiency,” Mramba told The Gu
SOURCE:
THE GUARDIAN