By Henry Mwangonde, The Citizen Correspondent
In Summary
If that is to happen, they are required to work day
and night despite all the challenges surrounding the multi-million
dollar project.
Dar es Salaam. One big question now hangs in the
minds of authorities managing the Dar es Salaam Rapid Transit (Dart)
project -- will they be able to complete it in time to allow President
Jakaya Kikwete to launch it before he leaves office come end of October?
If that is to happen, they are required to work
day and night despite all the challenges surrounding the multi-million
dollar project.
From the look of things the project won’t be
complete by the scheduled time -- September -- due to various challenges
including vandalism and delays in issuance of operation licences to bus
operators who are yet to be identified.
During his inspection tour yesterday, the minister
for Works, Dr John Magufuli, called upon STRABAG International GmbH, a
German construction company contracted to develop the project to
complete it in time.
The minister said the government was committed to
decongesting Dar es Salaam, and the project was one of the strategies
towards that end.
He said vandalism poses a threat to the life of
the project. “This is our project and we are all entitled to protect it
as the government has poured a lot of money and efforts into it,” he
said.
The project was launched in 2010 and was expected to be completed by end of this year.
The project trials, known technically as interim
operations, were expected to take off in April, but there are no rapid
buses yet. Neither have operators been issued with the necessary
licences. Dart is responsible for identifying, selecting and contracting
private operators.
For his part, Tanzania National Roads Agency boss
Patrick Mfugale said the first phase of the project has been completed
and can be handed over to Dart anytime.
The first phase includes the construction of 20.9 kilometre roads from Kimara to Kivukoni and from Morroco to Magomeni.
“The only remaining side now is from Kamata to Kivukoni but the whole project is 75 per cent complete,” he said.
No comments :
Post a Comment