Contractors are laying the infrastructure needed to build the
standard gauge railway as financiers prepare to release cash for the
biggest infrastructure project of the Jubilee government.
An
aerial view of the standard gauge railway construction site from the
skies provides an ideal impression of where the new track is going to
snake through.
From Mairakani to Athi River through
hinterland of the eight counties of Mombasa, Kilifi, Kwale, Makueni,
Taita Taveta, Kajiado, Machakos and Nairobi, the areas where the railway
will pass through are teeming with activity.
In some areas, the new rail line is just 70 metres from the old one.
On
this stretch, about 250 kilometres — of the 472 kilometre stretch from
Nairobi to Mombasa — of freshly excavated earth outlines the skeletal
frame of the track.
Alongside the track, the contractor is also lying ground for other services like fibre optic cables and power lines.
Even
though the initial trains for this line will be diesel-powered, the
contractors are leaving room for future installation of electricity.
LABORATORY
Dotting the path of the first phase of the railway are eight construction sites.
Sections
of the track will be fabricated and assembled at section six unit in
Kathekani and taken to the construction site in panels to be conjoined
into a seamless whole.
Laboratories to carry out tests on materials to be used for the construction are also up and running.
The
labs will test sand, ballast and soil density and dynamic penetration,
as well as cement superiority and steel yield stress among other
supplies.
At the Kathekani slipper and pre-cast beams
manufacturing site, which will supply the entire project, the factory is
now awaiting orders.
Staff at the 21 administrative
camps, which also comprise boarding houses, mixing and crashing plants,
laboratories among other facilities are on stand-by.
The
bulk of the work will be done by the main contractor, China Road and
Bridge Corporation (CRBC) who recently begun recruitment for local
staff.
The firm started preparing in November but the contract will take effect in January 2015.
However, on the stretch between Kibwezi East and Kibwezi West, not much activity can be seen.
This
is presumably due to the ongoing court case in which Kibwezi residents
sued the government for what they termed as inadequate compensation.
Through a case filed by Kibwezi West MP Patrick Musimba, the residents accused the government of measly payments for their land.
Mr
Musimba sought to stop construction of the railway through his
constituency arguing that the National Land Commission and the Kenya
Railways Corporation did not consult locals.
Nevertheless,
Kenya Railways Project Manager in charge of the SGR project, Eng
Maxwell Mengich says 85 per cent of the land required for the project
has already been acquired.
“We have acquired most of
the land from Mariakani to Athi River that is why you see work along the
corridor has taken off,” he said.
China Exim Bank,
which is funding 90 percent of the project (while the Kenyan government
funds the remaining 10 percent) had released 30 per cent of the Sh327
billion for the project last week, according to Mr Mengich.
“The rest will be released once the project takes off next year,” he added.
The contractor has already mobilised all the equipment needed to facilitate construction.
“We expect that by end of January, a three kilometre track will have been completed,” said Engineer Mengich.
“In
spite of the many distractions, the project is scheduled for completion
in May 2018. However, our target is to finish on June 2017.”
Of the ballast, the slippers, steel rails and fittings required for this project, only the last two will be imported from China.
CEMENT DELIVERY
“Because
the manufacturers of steel in Kenya cannot make the kind of quality
required in railway construction, then we are forced to import it.
However the cement will come from the local market.
The
contractor has given local manufacturers the quality required,” said
SGR business manager for external relations and cooperation James Chen.
Unlike
the old one, the new line will have two passenger and freight handling
stations in Mombasa and Nairobi. It will also have eight animal crossing
corridors.
Most of the area along the railway is inhabited by wild animals.
“The trains will thus be able to make non-stop trips ,” noted Engineer Mengich
No comments :
Post a Comment