Politics and policy
By KIARIE NJOROGE, gkiarie@ke.nationmedia.com
In Summary
- While the Ministry of Energy has consistently promised cheaper connectivity rate under the AfDB programme, a report prepared by Kenya Power suggests that only the vulnerable groups — widows, widowers, orphans and persons with disabilities — may benefit.
- Without any form of subsidy, however, the real cost of a single-phase connection stands at Sh135,000 while a three-phase connection requires Sh350,000.
- Under the Last Mile Connectivity, Kenya Power has set itself a target of building 47,200 kilometres of low voltage power lines to connect all potential customers within a 600-metre radius of its 35,000 transformers.
Electricity connection charges have nearly tripled in
the last two months despite the entry of the African Development Bank
(AfDB) in the campaign by the State to make the utility available to
poor rural households.
Under the AfDB-funded “Last Mile Connectivity Project” (LMCP), Kenya Power
is charging Sh91,000 on average for home users within a 600-metre
transformer radius, up from Sh35,000 that it used to levy before the
government withdrew its subsidy programme a few months ago.
While the Ministry of Energy has consistently
promised cheaper connectivity rate under the AfDB programme, a report
prepared by Kenya Power suggests that only the vulnerable groups —
widows, widowers, orphans and persons with disabilities — may benefit.
The electricity distributor wants the government to
use AfDB’s Sh13.4 billion grant to subsidise connection fee for the
vulnerable group, allowing them to continue paying at the old rate of
Sh35,000 which is to be staggered over time.
Without any form of subsidy, however, the real cost
of a single-phase connection stands at Sh135,000 while a three-phase
connection requires Sh350,000.
Under the Last Mile Connectivity, Kenya Power has
set itself a target of building 47,200 kilometres of low voltage power
lines to connect all potential customers within a 600-metre radius of
its 35,000 transformers.
The Sh58.2 billion project is expected to benefit 472,002 households near public amenities like schools and health centres.
According to an environmental and social report
conducted by the company in August, the model focuses on bringing the
power closest to the customer’s premises by extending the low voltage
network on existing and other upcoming transformers to reach households
lying within their radius.
“To reduce the cost burden of increased
connectivity on KPLC, as well as reduce the amount paid by the customer
to connect to the grid, the strategy proposed is to extend the
distribution network to as near the customer as possible using external
or government funding,” says the report.
“Thereafter the cost of connecting customers can be
at the maximisation rate based on the new average actual cost. The
number of customers to be reached with the proposed funding is 200,000
at a total cost of $153.4million (Sh13.7 billion).”
The report says that even at the subsidised cost of
Sh35,000, poor households were previously unable to connect as the
amount had to be paid up front.It advises that under the project that will be targeting poor rural households a deferred payment mode.
No comments :
Post a Comment