Politics and policy
Kenya Power staff repair power lines in Nyeri. The utility firm has
tendered for a novel single phase supply system that is expected to
lower the cost of electricity connections. PHOTO | FILE
By KIARIE NJOROGE
In Summary
- Electricity distributor has adopted a new design that reduces cost of construction material.
- The design will see Kenya Power use fewer cables and poles to connect households to the national grid at an average cost of Sh30,000.
- Experts say that besides lower material costs, the new design cuts other costs such as labour and transport expenses and allows for faster development of the network.
Electricity distributor Kenya Power
is adopting use of a new transmission lines design that is expected to
cut the cost of connecting new consumers to an average of Sh30,000.
The design, to be applied mainly in rural areas, will see
Kenya Power use fewer cables and poles to connect households to the
national grid.
Known as the Single Wire Earthing Return (SWER)
system, the design allows the power distributor to pull down connection
costs from the current average of Sh105,000 for homes seeking supply
within a radius of 600-metres from a transformer.
Lower cost of connection is to be realised through
use of single, thinner and lighter cables as opposed to the current
system that uses two or four cables to connect domestic consumers.
Kenya Power is also planning to cut costs by using
smaller poles that will be spaced 100 metres apart instead of the
current 50 metres.
“We are going to save on every aspect and this
should bring down connection rates within the 600 meter radius to an
average of Sh30,000 from the current Sh105,000,” Ben Chumo, the managing
director of Kenya Power said.
Use of the new technology comes as the Jubilee
government races to meet its target of connecting one million new
customers to the national grid in the fiscal year ending June 2015.
The twin obligations of meeting set government
targets and shouldering the burden of higher connection costs had left
Kenya Power in a fix – especially after the government withdrew a Sh2.7
billion subsidy it had offered to plug the financing gap between the
market cost of Sh105,000 and the Sh35,000 paid by consumers living
within 600 metres radius of a transformer.
“We have been overdesigning by using three phase
(commercial users) networks to connect new consumers yet 98 per cent of
new applicants are single phase users (domestic). It’s like using a
sledge hammer to kill a fly,” Dr Chumo said.
SWER is a single phase supply system with a single
conducting line that uses the earth as the return conductor. Metal rods
are driven two or three meters into the ground to provide the earth
connection.
Experts said that besides lower material costs, the
SWER design cuts other costs such as labour and transport expenses and
allows for faster development of the network.
“We will make savings on conductors, pole size and
population as well as transport and labour because of reduced use of
materials. These benefits will be transferred to our new customers,” Dr
Chumo said.
The new poles are similar to those hitherto used by
Telkom Kenya to carry telephone lines. The average price of the bigger
poles that Kenya Power uses is Sh12,000 compared to Sh8,000 for the
smaller poles. The conductors (cable) will be 25 millimetres squared
compared to the current 75mm² to 100mm².
SWER has been extensively used in New Zealand, Australia, Brazil, Canada and India in sparsely populated areas.
No comments :
Post a Comment