By EDWIN MUTAI, emutai@ke.nationmedia.com
In Summary
- Sh15 million had been paid to a contractor hired during the tenure of former registrar Gladys Shollei over and above the amount of work done.
Public Accounts Committee (PAC) Tuesday found out
that the Judiciary continues to lose millions of shillings in
pre-financed contracts despite the changes at the office of the Chief
Registrar.
Ms Anne Amadi, the Judiciary chief registrar said Sh15
million had been paid to a contractor hired during the tenure of her
predecessor over and above the amount of work done.
“This is the same dilemma that we continue to face.
When we dispatched our own inspection team to Kikuyu law courts to
ascertain whether the works for the Sh29 million Wide Local Area Network
had been completed, we realised what we paid was more than what was
delivered,” she told MPs while appearing before the House team to
respond to audit queries for the financial year 2013/14.
The committee also learnt that contracts for the
construction of eight prefabricated court houses had been pre-financed
yet contractors had not completed the work but are demanding for more
money.
The former Judiciary registrar Gladys Shollei has
since been charged in court. The committee yesterday heard that one firm
was given five contractors while another three contracts to put up
prefabricated court rooms in Kericho, Bomet, Wanguru, Othaya and Embu.
The judiciary paid in excess of Sh400 million for the construction of the court premises.
The works in the said towns have stalled following
investigations into the tendering processes that have seen the Ethics
and Anti-Corruption Commission take former registrar and other officials
to court.
“The issue of prefabricated court houses has been
discussed here before. It was occasioned by the fact that judiciary had
not court premises,” she said.
Ms Amadi revealed that she was the registrar when
Sh15 million more was paid to a company that connected the Kikuyu Law
Courts to the Wide Local Area Network (LAN).
“I was there when this happened. The ICT director
who was in charge of the first committee that recommended payment of
Sh29 million to the contractor has since been charged in court,” she
said.
Ms Amadi told the committee chaired by Jackson Rop
(Kipkelion) the second inspection team that was constituted to ascertain
whether the project had been completed realized that the firm had been
overpaid.
“The committee looked at the contract and the work
done and realized the company had been over paid by Sh15 million. We
have engaged the contractor to complete the works failing which we will
institute civil proceedings in court to recover the money,” she told
MPs.
Mr Rop, members Nicholas Gumbo, Sakwa Bunyasi and
Gonzi Rai expressed concern over the numerous contracts the judiciary
entered into and paid contractors in advance.
Mr Gumbo, the substantive PIC chairman said the
judiciary risk losing millions of money since it had paid contractors
money in advance.
“Payments have been made over and above the work so
far done. The contractors are still demanding more money to complete
the stalled projects. Was this not away of stealing money from the
Judiciary? How do you force someone who has been overpaid to complete
the project,” Gumbo asked.
No comments :
Post a Comment