The Government Tuesday moved to award
the Sh170 billion Lamu coal plant tender, even as other bidders say the
public stand to lose Sh19 billion in extra costs.
In a letter sent on Tuesday to the best evaluated bidder, Gulf Energy, Energy Principal Secretary Joseph Njoroge informed the consortium that they can go ahead and negotiate with Kenya Power on pricing.
In a letter sent on Tuesday to the best evaluated bidder, Gulf Energy, Energy Principal Secretary Joseph Njoroge informed the consortium that they can go ahead and negotiate with Kenya Power on pricing.
Successful
negotiations over the cost of buying the power will be followed by
contract signing, paving the way for implementation of the flagship
project for the 5000 MW+, the Jubilee Government’s power masterplan.
“Your bid was successful and accepted on 10 parameters. The Ministry will invite your team to negotiate for time and cost of the project,” Mr Njoroge notes in the correspondence seen by the Nation.
“Your bid was successful and accepted on 10 parameters. The Ministry will invite your team to negotiate for time and cost of the project,” Mr Njoroge notes in the correspondence seen by the Nation.
“These
parameters will form the basis of negotiations for the Power Purchase
Agreement (PPA) and must be verified,” the letter says. The issue of
pricing, however, is raising heat... with one of the losers saying
Gulf’s bid amounts to Sh19 billion each year as extra costs to
consumers.
In total, it is said the public will pay
Sh475 billion in additional cost in electricity bills if the award goes
to Gulf Energy, given that the project is expected to run for 25 years.
Two
Chinese firms — HCIG Energy which teamed up with a Kenyan registered
firm, Liketh Investments, and a Shanghai-led consortium — were the
losers, although they were initially considered as being responsive.
On
Monday, at a status meeting, the losing bidders criticised the
ministry’s tender committee for what they termed as awarding of the
tender to the highest bidder. While the tender award was slated for June
and commissioning on September 1, the process has been delayed.
CONSTRUCTION WILL LAST 21 MONTHS
Gulf
Energy, however, says they are ready to start, with a finish date of
2017. “We hope, with facilitation by the Government, to reach financial
closure within six months. Construction of the plant will last 21
months,” said a top Gulf Energy official.
The winning
consortium has said it would sell power at US cents 7.56 per kilowatt
hour (kwh), subject to prevailing international coal prices.
The
two Chinese companies also claim that the consortium led by Gulf Energy
was favoured during the process, first being allowed to change their
partners, replacing Tata group with Centum Investment, which is against
the rules.
The Gulf-led consortium was also evaluated
on a price of $100 per tonne of coal against the $50/mt stipulated in
the bid documents, the benchmark for evaluating the other bidders.
A
tender evaluation official Tuesday accused both the Chinese firms of
attempts to change the Specific Fuel component, a key element which
determines the cost of the plant, saying this amounted to change in
substance of the original bids and prices.
“The numbers provided by these two were not adding up when tested against the applicable formula,” the official said
No comments :
Post a Comment