By WANGUI MAINA
In Summary
- Capacity at Jomo Kenyatta International Airport is set to increase by over four million passengers in the next six months following the approval of a loan by the African Development Bank and fast-tracking of Unit 4.
- The 10,000 square metre temporary terminal, which is expected to be in place in four months, will cost Sh2.34 billion ($27.6 million). The AfDB last week approved a Sh2.3 billion ($27.1 million) loan for the construction of the terminal, with the Kenyan government meeting the difference of Sh42 million.
Capacity at Jomo Kenyatta International Airport
is set to increase by over four million passengers in the next six
months following the approval of a loan by the African Development Bank
and fast-tracking of Unit 4.
The 10,000 square metre temporary terminal, which
is expected to be in place in four months, will cost Sh2.34 billion
($27.6 million). The AfDB last week approved a Sh2.3 billion ($27.1
million) loan for the construction of the terminal, with the Kenyan
government meeting the difference of Sh42 million.
The interim terminal has a capacity of 2.5 million passengers, or 6,850 people per day.
The Kenya Airports Authority (KAA) closed the
tender process last Friday, having invited bids for the supply of
design, and installation of the terminal in September, with each bidder
putting a security of Sh42.4 million ($500,000).
“We tendered to buy the equipment. We want it in
place in the next four months,” said KAA’s finance general manager, John
Thumbi on Friday on the sideline of a Kenya Airways event at JKIA.
“This temporary airport is a measure as we wait
for Greenfield to start and become operational,” he said. The Greenfield
project caused uproar when it emerged that the tender for the
construction of the terminal was given to two Chinese companies by the
KAA management in December 2011 without the approval of the board.
Gabriel Negatu, AfDB’s regional director for
eastern Africa, said the financing was not a new loan but part of
savings made from recently completed bank-financed projects under the
bank’s concessionary window – Africa Development Fund.
In addition the development bank approved a Sh84
million ($1 million) grant to enhance security at the airport. The
equipment, including eight walk through metal detectors, eight check-in
x-ray machines and nine cabin x-ray machines will replace some of the
ageing equipment at the airport and those that were destroyed by the
fire.
The grant was provided as an emergency assistance
support under the Bank’s Special Relief Fund in one tranche and
installation is expected to be done within the next six months.
Following the incident the government has set the
completion of Unit 4, with a capacity of 2.5 million passengers for the
end of the year as opposed to March 2014. JKIA handles up to six million
passengers annually with a capacity of 1.5 million.