Summary
·
Each of
the three nations is set to receive a supply of 26.67 megawatts once the power
project start generation
Rusumo. The transboundary 80-megawatt Rusumo Hydropower Project has emerged as a testament to
the power of regional collaboration, demonstrating its potential for transforming energy landscapes.Currently, at 99.6 percent
completion, this joint venture between the governments of Tanzania, Rwanda, and
Burundi has brought together an investment of nearly $468 million.
For the implementation of the
Regional Hydroelectric project and the Power transmission lines, the World Bank
and African Development Bank advanced $340 million and $128 million,
respectively to the three countries.
Each of the three nations is set to
receive a supply of 26.67 megawatts. During a recent visit to the project site,
The Citizen learned from the project manager, Mr Alloyce Oduor, that the
undertaking is in the most exciting commissioning phase.
Commissioning test procedures are
used during the final phase of the plant.
These procedures outline tests to be
performed on the major plant systems to ensure all elements of the system
operate as designed, and interface with the entire system completely.
According to Mr Oduor, the
completion of the commissioning process for generator number one is scheduled
for the end of July this year.
Subsequently, the commissioning of
unit two will take place in August, followed by unit three in September 2023.
He said that if all the necessary
tests and inspections have been passed satisfactorily, the generating unit will
be ready to enter commercial operation.
“When we finalise all the
commissioning tests and the units have been declared operational, we declare
what is called the Commercial Operation Date (COD), and then Rusumo Power
Company Limited (RPCL) takes over,” he said.
RPCL is a special purpose company
incorporated by the three countries to develop, construct, own, and operate the
Rusumo Hydropower Project.
The experts agreed that this
project, located at the Rusumo Falls, at the shared border of Rwanda and
Tanzania on the River Kagera, will significantly increase the installed
capacity for electricity generation in the region and promote a shift towards
renewable energy sources.
Nestled within the picturesque
landscapes of East Africa, the Rusumo River serves as a lifeline to the
surrounding communities, cascading with untapped potential.
Recognising the immense value of
this shared resource, Tanzania, Rwanda, and Burundi embarked on a historic
joint venture to harness its power through the construction of a
state-of-the-art hydropower plant.
The project is being implemented
under the Nile Equatorial Lakes Subsidiary Action Programme (NELSAP).
For Tanzania, this project is poised
to be a significant boost to the national power grid, extending far beyond just
meeting Tanzania’s energy demands but also catalysing the growth of various
sectors, such as manufacturing, agriculture, and infrastructure.
Mr Oduor said this endeavour
showcases the collective determination to achieve sustainable development and
sets a precedent for future cross-border initiatives across the continent.
The project implementation became
effective in 2017 and was supposed to be completed within a 36-month time
period.
“There were delays, which are very
normal and common in a major project like this. So we did not attain
those dates,” explained Mr Oduor.
One of the major challenges, he
said, was the positioning of the project at the border, where there were a lot
of cross-border movement issues and paperwork that was sluggish.
“Facilitation of labour and
materials from one territory to another was a bit of a challenge, and secondly,
the structure of the project implementation was in such a way that managing the
interface between two contractors was quite challenging,” he said.
He said the Covd-19 pandemic also
interfered with the supply chains and disrupted a number of construction
activities, resulting in delaying the deadline.
The Rusumo project’s chief resident
engineer, Mr Bosco Mugabo said working on the facility has been a special
experience for regional integration as the three countries put resources
together and improved the know-how for their communities.
“We have integrated Tanzanians,
Rwandans, and Burundians into a project. It has shown that it is possible
to implement such projects,” he said.
“Reaching this stage (99 percent
completion) is actually a very big achievement,” said Mr Mugabo.
Learning from mistakes
However, the project engineer said
this success came with its challenges, as there were a lot of administrative,
technical, and financial setbacks during the implementation.
“There were issues with visas and
permits, among other challenges. But there is room for improvement in the
future,” said Mr Mugabo.
The hydropower plant will harness
the renewable energy potential of the Rusumo River, replacing fossil
fuel-dependent sources and significantly reducing greenhouse gas emissions.
This will align with the Tanzanian
national agenda on transitioning to clean energy.
According to NELSAP, contractors
also developed detailed assessments and mitigation plans covering all aspects
of environmental, social, health, and safety concerns.
This included management plans and
comprehensive measures to mitigate ecological impacts, ensure the preservation
of aquatic ecosystems, and safeguard the delicate balance of the region’s
biodiversity.
Rusumo Project is giving back to the
riparian communities surrounding Rusumo Project’s construction area by
implementing the Local Area Development Programme (LADP), a benefit-sharing
programme worth $15 million.
Through LADP, the construction of
the Rusumo Project has the potential to transform the lives of rural
communities along the river’s course.
In Tanzania, such social projects
included the rehabilitation of water systems in four villages (Mshikamano,
Kasulo, Rwakalemela, and Kasharazi), the construction of Rusumo Health Centre,
the improvement of Lemela Focal Community Development College (FDC), the rehabilitation
of two workshops, and the construction of a playing ground.
Others are the construction of
Bukiriro Secondary School, the construction of Lukole Health Centre, the
construction and rehabilitation of Rusumo Secondary School buildings, the construction
of Rusumo dispensary in Kyenda Village, the construction of Mumiterama
Secondary School, and the construction of Rusumo Primary School.
LADP coordinator in Tanzania, Ms
Irene Chalamila, said all these initiatives have supported and improved the provision
of basic services in the surrounding communities.
Tanzania LADP has also constructed
Lukole Health Centre, which is currently functional, staffed, and equipped with
all necessities such as medication blocks, convenient toilets, a mortuary, a
theatre, a labour ward, and an incinerator, as well as accommodation for health
centre staff.
In Rwanda, a notable project in the
rehabilitation and extension of a water system in Ngoma district at
Gatonde-Gahima cells will benefit about 10,000 people.
Tabling the Energy Ministry’s
2023/24 fiscal year, the Minister for Energy, Mr January Makamba, said power
generation plants connected to the national grid have the capacity of producing
1,872.04 Megawatts, a 10.5 percent improvement from the 1,694.55 Megawatts that
were reported at the end of the 2021/22 fiscal year.
According to the minister, there is
also a rise in demand, which is attributed to the increased number of large
customers, especially industries and businesses, which have increased by 5.6
percent, as well as the growth in economic and social activities.
“The electricity demand in the
country has continued to grow; during the period of 2022/23, the average
electricity demand was 1,363.94 MW, representing a 6.9 percent increase
compared to the average of 1,276.43 MW in 2021/22,” he said.
“During this period, the peak
electricity demand has increased to 1,431.59 MW (as of May 15, 2023, at 2:00
AM), showing a 6.8 percent increase compared to the 1,340.68 MW reached in
2021/22 (as of May 26, 2022, at 2:00 AM),” said the minister.
For 2023/2024, out of the entire
Sh3.049 trillion budgeted, a staggering Sh2.96 trillion—which translates into
97.1 percent of the ministry’s total budget—will be spent on development
projects.
Mr Makamba said this huge investment
is important because the existing electricity production in the country does
not align with the rapidly growing economic and social activities, resulting in
a significant infrastructure deficit for electricity transmission and
distribution.
The regional Rusumo Falls Project
will also have transmission lines associated with the Power Plant facility.
Each of the three partner
governments and its utility company will be responsible for the evacuation of
power from the power plant.
Three 220kV transmission lines shall
be constructed to connect the power plant substation to the respective centres
within each country, such as 94km from Rusumo Falls to Nyakanazi in Tanzania,
161km from Rusumo Falls to Gitega (Burundi), and 119km from Rusumo Falls to
Shango and Bugesera (Rwanda).
On the Tanzanian side, according to
the minister, the transmission lines were completed by February 2023.
In his budget speech, Mr Makamba
said the development of the transmission lines had cost $35 million, equivalent
to Sh81.41 billion.
The African Development Bank (AfDB)
contributed $33.7 million, and the government injected $1.3 million.
According to the minister, there is
also a rise in demand which is attributed to the increased number of large
customers, especially industries and businesses, which have increased by 5.6
percent, as well as the growth in economic and social activities.
“The electricity demand in the
country has continued to grow, where during the period of 2022/23, the average
electricity demand was 1,363.94 MW, representing a 6.9 percent increase
compared to the average of 1,276.43 MW in 2021/22,” he said.
“During this period, the peak
electricity demand has increased to 1,431.59 MW (as of May 15, 2023, at 2:00
AM), showing a 6.8 percent increase compared to the 1,340.68 MW reached in
2021/22 (as of May 26, 2022, at 2:00 AM),” said the minister.
For the 2023/2024 out of the entire
Sh3.049 trillion budgeted, a staggering Sh2.96 trillion – which translates into
97.1 percent of the ministry’s total budget will be spent on development
projects.
Minister Makamba said this huge
investment is important because the existing electricity production in the
country does not align with the rapidly growing economic and social activities,
resulting in a significant infrastructure deficit for electricity transmission
and distribution.
The regional Rusumo Falls Project
will also have transmission lines associated with the Power Plant facility.
Each of the three partner
governments and its Utility Company will be responsible for the evacuation of
power from the power plant.
Three 220kV transmission lines shall
be constructed to connect the power plant substation to the respective centers
within each country such as 94km from Rusumo Falls to Nyakanazi in Tanzania,
161km lines from Rusumo Falls to Gitega (Burundi) and 119km lines from Rusumo
Falls to Shango and Bugesera (Rwanda).
On the Tanzania side according to
the minister, the transmission lines were completed by February 2023.
In his budget speech, Mr Makamba
said the development of the transmission lines had cost $35 million equivalent
to Sh81.41 billion.
The African Development Bank (AfDB)
contributed $33.7 million and the government injected $1.3 million.
No comments:
Post a Comment