Dar es Salaam —
Negotiations for a Host Government Agreement (HGA) for the East African
Crude Oil Pipe-line (EACOP) project will start soon, The Citizen has
learnt.
This follows
completion of Total Oil's acquisition of 33.334 percent of Tullow Oil's
stake thus paving
the way for the French oil giant to own a 66.7 percent
of upstream stake in the project.
Also, this has given it legal ownership and the right to fast-track execution of the project.
The HGA is an
agreement between a foreign investor and the local government which is
intended to reduce financial and political risks posed to investors by
sudden changes in national laws.
The HGA outlines
issues pertaining to tax and other revenues to be accrued from the
project; participation of Tanzanians in the project and how to deal with
challenges that might arise during implementation of the project.
HGA talks with Tanzania will start after the talks between Total Oil and Uganda are concluded.
Also Read
Why affordability of smartphones crucial in Covid-19 Fight
Earnings from forex trade dive as Covid-19 bites
Tigo Pesa customers to share Sh2.7 billion quarterly profit
They will also come
after the completion and issuance of an environmental impact assessment
certificate by the National Environment Management Council (Nemc).
The EACOP national
coordinator, Salum Mnuna, told The Citizen earlier this week that
Tanzania's preparations for the HGA negotiations are at an advanced
stage, and the talks would start anytime now.
"The team which is
currently undertaking HGA negotiations in Uganda is the one that will
engage with us here," he said adding that the target is to have the
negotiations finalised by the end of September this year, so that
further development activities can continue.
Upon completion of the HGA negotiations, focus will shift to other aspects of the project, including Land Lease
Tenure, Shareholders Agreement (SHA) and the Ports Agreement.
According to Mr Mnuna, negotiations on the Land Lease Tenure are currently under the Chief Valuer.
"Once the
agreements are completed, the project will reach the Final Investment
Decision (FID) which sets the stage for further development of the
project," he said.
The FID is the
crucial step in a project that tells investors and shareholders that
companies are ready to spend money on a new project, and that they
expect the project, once fully operational, to make enough money to make
the initial investment worth it.
Energy minister
Medard Kalemani recently told Parliament that the project was expected
to commence in April, 2021 after finalization of the FID.
He said during the
2020/21 financial year, the government would complete the ongoing social
engagement with key stakeholders. It will also complete payment of the
remaining Sh1 billion in compensations.
Earlier this month,
a Total delegation led by President, exploration and production Arnaud
Breuillac held talks with Energy Minister Medard Kalemani whereby they
updated the Tanzania government on the new development.
Mr Breuillac said
following recession in the global economy as a result of the Covid-19
outbreak, various international tender offers would be revised to
reflect to the current market conditions.
Speaking during the
meeting, Dr Kalemani said Total Oil has accepted his request to fast
track the project expected to start in early 2021 and be completed
before the 36 months set in the deadline.
"This is because the project has been delayed already," he said.
The Uganda
government delayed sale of Tullow shares for months over tax issues
until expiry of the Production Sharing Agreement (PSA) leading to
stalling of the project.
In September, 2019,
Tanzania Petroleum Development Corporation (TPDC) director general
James Mataragio said the reasons that caused the project to stall are
normal in such under-takings, hence assured the public that the project
would be implemented as per plans.