A deserted construction site at Itare Dam in Kuresoi South, Nakuru County on October 9, 2018. FILE PHOTO | NATION MEDIA GROUP
An Italian firm contracted by the national government to
construct the multibillion Itare Dam within Nakuru County has denied
claims that it is broke.
In a
statement to newsrooms, CMC di Ravenna said that neither itself nor its
subsidiaries have been declared bankrupt or insolvent.
“CMC
has voluntarily engaged in a composition with creditors procedure to
ensure it safeguards the interests of all stakeholders (creditors,
investors, clients and co-operative employees),” the statement read.
“CMC di Ravenna continues to be fully committed to completing the dam project ahead of or within the contracted time frame.”
But the firm attributed the slow work pace to delays in receipt of payments.
According
to the company, as at November 2018 its forward order book amounted to
£4.7 billion, a process initiated by CMC board to ensure full
transparency and financial compliance.
Contracted
to complete the dam by 2021, the firm said 30 percent of the works
already finished in the project that started in April 2017.
The firm said it will resume operations in March following the temporary suspension.
Background
CMC
di Ravenna is one of the biggest construction firms in Europe but it
has hit financial turbulence in recent times and was declared insolvent
by an Italian court last December, thus putting in doubt its ability to
undertake massive projects to completion.
The Nation has learnt the government has already paid the company Sh11 billion out of the total Sh38.5 billion budgeted for Itare Dam.
It
has also emerged the troubled construction conglomerate is in fact
holding contracts of five dams, and not three, as earlier reported.
The Nation
learnt the company also won tenders to construct Radat Dam in Marigat,
Baringo County, at a cost of Sh20 billion, and Kithinu dam in Nkubu,
Meru County, at a cost of Sh26 billion.
This
is besides three other mega dams the company is constructing in Rift
Valley region — Itare dam in Nakuru County at a cost of Sh38 billion,
Arror Dam for Sh38 billion and Kimwarer Dam for Sh28 billion.