Dams are emerging as the new conduits of corruption following
reports after reports said President Uhuru Kenyatta reshuffled his
principal secretaries following the proposed Sh62.3 billion Thwake Dam
tiff.
Top government sources on Sunday revealed that Mr
Patrick Nduati, former Water and Irrigation PS, was spared the sack by
the President, who was unhappy with the controversy surrounding the
contract pitting him against his Cabinet Secretary, Mr Eugene Wamalwa.
While
that tussle has been ended with Mr Nduati’s departure, the decision
awaits the outcome of an appeal filed at the Public Procurement
Administrative Review Board (PPARB) by China Gezhouba Construction Group
Corporation. The company lost out despite having submitted the lowest
bid and got the clearance of the African Development Bank (AfDB),
co-funders of the project.
“The President was not
happy about the whole controversy,” said the source. “After a briefing
with those concerned, he decided to make a reshuffle of accounting
officers with Mr Nduati as the target.
AWARDING CONTRACT
“He is concerned about the need for the country to have enough water for irrigation to make Kenya food-secure.”
The Ethics and Anti-Corruption Commission (EACC) investigated
the matter and advised against awarding the contract. Attorney-General
Githu Muigai also gave a negative opinion on the company which the PS
insisted on giving the contract, it emerged.
The
controversy was only the latest in a string of disputes that have marked
the construction of dams and delayed the benefits to millions of
Kenyans. As the new Irrigation PS, Ms Zeinab Hussein was handed the
onerous task of ensuring that funds are not lost through the contract.
On
Sunday, the chairman of the National Assembly’s Agriculture Committee
said the concerns of Members of Parliament were that, while the project
had been mooted in 2013 and pre-qualification of the firms in the tender
had begun in 2015, the whole thing was taking very long.
“We
wanted to correct issues but there was a lot of distortion of the
story,” said Mr Adan Nooru. “We were concerned that everything that
touches on food security in this country is not taking off.
“The
only way of getting food security is irrigating arable land. The whole
concept was good but the implementation has been a problem.
“It is failing or is not taking off.”
“It is failing or is not taking off.”
REPORTS OF CORRUPTION
The
same could as well be said of other dam projects that have been
characterised by reports of corruption, delayed payments to contractors,
resistance by communities near the proposed sites and demands for
compensation by those being relocated.
In Kitui
County, Mrs Charity Ngilu, the then-Water minister, led residents in
ejecting the contractor from the site, escalating a row that resulted in
the abandonment of the Umaa project.
The dispute had
to be settled through arbitration but the end result was that a dam
initially set to cost Sh800 million will now cost Sh400 million more and
construction will probably end eight years after construction began.
Umaa
was one of five dams that the Kibaki administration started. Only three
had been commissioned, with legal disputes delaying the other two. The
dams started over the past seven years are Maruba, Chemusus, Umma,
Kiserian and Badasa.
In Tharaka-Nithi, problems have
started even before construction of the biggest water project in recent
years, the High Grand Falls Dam. The dam is budgeted to cost Sh150
billion and is expected to hold over 5.6 billion cubic metres of water
that will be used to irrigate over 250,000 hectares of land and produce
more than 700 megawatts of electricity.
The plan
could, however, be delayed by demands for compensation led by Governor
Samuel Ragwa, who has said that those to be moved relocated should be
paid at the same rate as those who moved for the standard gauge railway.
DENIED ACCESS
Last April, Baringo residents denied geologists access to the proposed site of the Sh5 billion Radat Mega Dam.
Lost
in the reports about the scam at the National Youth Service (NYS) was
the revelation that the agency had lied that it was constructing dams.
The
NYS had been given Sh3.6 billion in the 2013/14 Budget for the
construction of dams, which was more than half the amount Parliament had
approved for the projects. Of that, Sh3.1 billion was committed by the
NYS for the job, the Auditor-General said in his report of the special
audit of the institution.
However, said the
Auditor-General, only Sh1.8 billion was transferred to the
then-Environment ministry by the Planning Department with the work being
done by NYS servicemen. In its report on, the NYS said 212 were being
constructed.
When auditors went to 35 locations in October 2015, they were surprised.
“All of the facilities visited were ‘water pans’ and not ‘water dams’ as had been indicated,” said the auditor.
The
report concluded that it could not verify whether the Sh1.8 billion was
well spent as there were no records while the cost of the job could
also not be established because the construction and the manpower was
from the NYS.
No comments:
Post a Comment