Kenya Power is set to lose the muscle to determine the
electricity mix to be sold to consumers under a new plan to establish an
independent player to decide which energy plants are to be fed to the
national grid.
The Energy Regulatory Commission
(ERC) on Monday said plans are afoot to set up a national load dispatch
centre, which will be charged with scheduling feeding of electricity to
homes and industries starting with the cheapest options such as hydro
and geothermal.
The Kenya Electricity
Transmission Co Ltd (Ketraco) will manage the facility, the regulator
said, and will ensure that plants generating cheaper power are
dispatched to the grid first and other costly options brought on-stream
as demand increases.
“We want an independent
system operator who has a helicopter view on power demand and supply and
makes decisions on the most optimum and economical mix,” said ERC
director-general Joe Ng’ang’a on Monday.
“An independent player will remove any conflict of interest,” said Mr Ng’ang’a in an interview.
Kenya
is following in the footsteps of countries such as India and Malaysia,
which have national load dispatch centres — a central authority which
monitors demand and supplies power to the retailer starting with the
least cost source, technically known as economic merit order dispatch.
Kenya’s
energy mix includes hydropower as the cheapest source priced at ¢3 per
kilowatt-hour followed by Mumias co-generation (¢6 per kWh), geothermal
at ¢7 per unit, Biojoule’s biogas (¢10 per kWh), and Strathmore
University’s solar power is priced at ¢12 per unit.
Thermal power is priced at ¢20 per kWh while emergency power costs cost nearly double the price of diesel-fired electricity.
This
new plan leaves Kenya Power as the electricity retail monopoly —
selling to homes and factories from sources determined by the dispatch
centre.
Kenya Power Managing Director Ben Chumo was yet to respond to our inquiries by the time of going to press.
Ketraco
on Monday floated a tender seeking consultants to carry out a
feasibility study on setting up the national load dispatch centre.
Mr Ng’ang’a said the facility will be set up once the Energy Bill, currently before the National Assembly, is passed.
The
fresh impetus to set up an electricity dispatch platform comes on the
back of Kenya Power’s increasing appetite for expensive thermal power
despite the injection of 280 megawatts of cheaper geothermal power from
Olkaria.