Money Markets
By JOHN GACHIRI, jgachir@ke.nationmedia.com
In Summary
Kipeto Energy’s Kajiado-based wind-power project has
gathered pace after it awarded a Chinese firm the multi-billion contract
to construct the plant.
China Machinery Engineering Corporation clinched the Sh22.6
billion contract for the engineering design, procurement and
construction (EPC) of the wind farm that is set to generate 100
megawatts (MW).
The project, one of the largest US foreign direct
investments in Kenya, will be completed within two years from the date
of commissioning which was not disclosed.
“The company, as the EPC general contractor, will
be responsible for the design, supply, civil engineering and
construction, installation, training, commissioning, technical services
and other works of the Project on a turnkey basis. The contract value
amounts to $221 million (Sh22.6 billion),” said the firm in regulatory
filings.
“As stipulated in the contract, the project
construction will commence upon the satisfaction of certain conditions
precedent. The construction period of the project will last
approximately 22.5 months once the construction is commenced.”
China Machinery Engineering Corporation is a construction and engineering firm listed on the Hong Kong Stock Exchange.
Ground work for the project has been going on, with
the company already having signed a 20-year power purchase agreement
with electricity distributer Kenya Power for an undisclosed amount in 2015.
Kipeto Power also entered into an agreement with US
conglomerate GE in July last year for supply of 60 GE 1.7-103 wind
turbines at the Oldonyo-based site.
The Overseas Private Investment Corporation (OPIC),
the US government’s development finance arm, is providing debt
financing of $233 million (Sh24 billion).
The African Infrastructure Investment Fund II is
the largest project shareholder with a 55 per cent stake, followed by
Craftskills Wind Energy International Ltd and IFC, which have a 20 per
cent stake each with the Kipeto Local Community Trust owning the
remaining five per cent stake in the project.
Wind energy is emerging as a key energy source,
with a number of power plants in the pipeline. Lake Turkana Wind
Project, which is the largest wind plant in Africa and currently under
construction, will produce 310 MW when completed in June 2017.
KenGen
is also scaling up wind production which it expects to account for up
to six per cent of its energy mix by 2020, up from the current two per
cent.
A coverage report by Exotix says the listed power
generator will produce 140MW , of the projected 2,363MW that KenGen is
projected to produce, from wind.
KenGen produces 26MW of wind energy at its
Ngong-based site but it is looking at the possibility of additional
power from wind and geothermal sources.
No comments:
Post a Comment