By GEORGE BODO
In Summary
- Accumulation of pending payments has reduced banks’ appetite for road construction projects.
It seems funding of road contractors is becoming a
tricky business for banks and nearly all commercial banks that have
reported a surge in non-perfoming loans cite customers linked to road
construction as part of the problem.
KCB’s
Q3 provision for bad loans doubled on a quarter-on-quarter basis, and
in answering the next obvious question, the bank said it had to fully
provide for, among others, some accounts in the construction sector
linked to government payments (which can only be road contractors whose
payments have been delayed).
A similar story came out sometime back when Standard Chartered
bank shocked the market after reporting a 300 per cent year-to-date
growth in its non-perfoming loans portfolio at the close of the second
quarter.
And there are many more such cases in the banking sector that remain unreported.
Indeed there’s a massive delay in payments to
contractors by the government. At the close of 2013, the value of road
works yet to be certified totalled Sh88 billion. At the close of April
2014, pending approved payments totalled Sh25 billion.
Data from Central Bank of Kenya (CBK) shows that
the share of non-perfoming loans (NPLs) in the building and construction
sector, as percentage of total industry NPLs, recorded the biggest
growth between December 2010 and September 2014; rising from just 2.4
per cent at the close of 2010 to 10 per cent as at third quarter, and
could rise further in 2015 if the delay continues.
This accumulation of pending payments has not only
reduced banks’ appetite for road construction projects, but has also
eroded confidence between the government on one side, and contractors
and banks on the other.
As part of confidence rebuilding, the government
plans to allocate Sh16 billion in the second supplementary budget for
the current fiscal year 2014/15 to help clear some of the outstanding
payments to contractors.
The government is very keen in building this
much-needed confidence because they’ve now built a new solution to the
problem; and the solution is that the Ministry of Transport is
implementing the new annuity programme of financing road construction.
Under this new programme, contractors will obtain
loans from banks to construct roads, but get paid back by the Treasury
through regular disbursements each year for up to eight years.
It is a design, build, finance and maintain model
whereby the contractors will negotiate for financing from banks before
submitting their bids. A contract will be won on the basis of the lowest
annuity payments.
There will pre-agreed milestones between government
and contractors, and upon certification, banks will release money. A
contractor will then be responsible for maintaining the road(s) for up
to eight years.
And the government has rolled out an ambitious plan of building 10,000 kilometres of roads in four years under this programme.
But the difference between the current model and
this new annuity programme is that the government has established
mechanisms to ring-fence annual budgetary allocations for the annuity
programme from the usual politics and outright embezzlement, through the
creation of a Roads Annuity Fund which will be managed by an
independent board; and even the money wired to the fund will sit in an
escrow account (complete with a very complex access procedure).
The government, in its own analysis, says it will
require nearly Sh47 billion for yearly payment of annuity for 3,000
kilometres of roads.